An EPC contractor tracks BOQ, RA bills and site costs on one system

BOQ-based estimating, site procurement, subcontractor RA bills and project costing on ERPNext for a building contractor running industrial, institutional and residential projects.

to raise a client RA bill
−9 days
to raise a client RA bill
live sites on one system
30+
live sites on one system
cost-to-complete by project
Weekly
cost-to-complete by project
TDS and GST on subcontractor bills
100%
TDS and GST on subcontractor bills

The client

PSP Projects builds industrial, institutional, government and residential projects across Gujarat and other states. Each project runs on a BOQ, with materials bought at site and much of the work done by subcontractors billed on running-account (RA) bills.

The challenge

  • ✕BOQs lived in Excel and were re-entered for every client RA bill.
  • ✕Site purchases were approved by phone and booked weeks later.
  • ✕Subcontractor bills were checked against measurement books by hand.
  • ✕Cost-to-complete was estimated only at quarterly reviews.

The solution

BOQ and estimates

BOQs imported per project, with rates, quantities and amendments version-controlled.

Site procurement

Indents, approvals and goods receipts on mobile at site, posted to the project in real time.

RA billing

Client and subcontractor RA bills generated from measurements, with retention, TDS and GST applied.

Project costing

Budget, committed and actual cost by BOQ item, with cost-to-complete every week.

How we delivered

  1. 01Pilot on three sites before company-wide rollout.
  2. 02Site engineers trained on mobile entry in two-hour sessions.
  3. 03Historical BOQs and open RA bills migrated for live projects.
  4. 04Monthly review with project heads for the first two quarters.

The results

  • ✓Client RA bills go out nine days sooner.
  • ✓Every site purchase is booked the day it happens.
  • ✓Project heads see cost-to-complete weekly.
  • ✓Subcontractor TDS and GST are applied without manual checks.
“We used to find out a project was over budget at the quarterly review. Now we see it in the weekly report.”
Director, Projects, PSP Projects